So let’s play a little “DIS Construction Schedule Expert” with the room work to date. Just for kicks. Because of course we're all experts here.
Mid November 2020 - Scaffolding/Walls Erected outside of Tuvalu (56 rooms), Fiji (66 rooms), and Aotearoa (89 rooms) (total of 211, or 44% of Poly's regular hotel room inventory)
Late December 2020 - Images of gutted first floor rooms, plastic up on the rest
Early March 2021 - Finished room in Tuvalu revealed (seems like it was 3414)
So in round numbers, 3.5-4 months.
Now, are all three longhouses on similar schedules with rooms at/nearing completion? Or was what they showed us just an early completion and the rest are a long way from being done? Million dollar question I guess.
With walls/the beginnings of work now moving to the other longhouses - Rarotonga (89 rooms), Niue (22 rooms), Somoa (54 rooms) and Hawaii (102 rooms) (total of 267 rooms, or 56% of Poly's regular hotel room inventory)....4 months puts it at mid-July.
I'm still going to say 7/19 opens with some longhouses open and others still being completed - but TBD of course!!!!
(Note, room counts are approximate, did not include Tonga suites in the above for simplicity)