Based on the progress to date, do you all think we will have a good chance to request and receive a refurbished room when we check in on November 24?
I keep trying to logic this out with what little we know so far. If it takes 3 months per building (this started in early March and reportedly no new rooms open till June), and they overlap a month between buildings (report here that they started closing/gutting Bldg 9 in early May while still working on Bldg 8)...
I'm speculating on one new building opening every 2 months starting in June. Which would mean:
Bldg 8 (90s) open early June.
Bldg 9 (80s) open early August
7 - Oct
10 - Dec
6 - Feb
and so on. This puts them past the supposed May 2018 completion, but I don't see how they make that without speeding up BIG time.